Five of India's 12 Approved Chip Plants Are Now Running, but All Five Package Chips and the First Fab Is Due in 2028

Illustration by tuput

English

By 17 September 2026 the India Semiconductor Mission had approved 12 plants with investment of more than Rs 1.64 lakh crore, and five were in commercial production. Micron, Kaynes, CG Semi, CDIL and Suchi Semicon assemble and test chips, while Tata Electronics' Dholera fab, the programme's one silicon fab, is scheduled for 2028.

· · 8 min read

On 17 September 2026 the government counted 12 semiconductor plants approved under the India Semiconductor Mission, with investment of more than Rs 1.64 lakh crore, and five of them in commercial production. The Press Information Bureau (PIB), the government’s release service, calls all five assembly, test and packaging units. The programme’s one silicon fab, Tata Electronics’ plant at Dholera in Gujarat, is not among them, and a PIB release of 15 July 2026 says the first fab is scheduled to be commissioned in 2028.

The two kinds of plant do different jobs. A fab (fabrication plant) prints circuits onto silicon wafers. An ATMP or OSAT plant (assembly, testing, marking and packaging, or outsourced semiconductor assembly and test) takes finished circuits, mounts them in protective packages and tests them. The Dholera fab alone is listed at Rs 91,526 crore, more than half of the programme’s total.

What the programme pays, and why the figures differ

The Semicon India programme, notified on 21 December 2021, started with an outlay of Rs 76,000 crore. The mission’s own page says it offers 50 percent fiscal support on a pari passu basis, meaning the government pays its half in step with the company’s own spending. Micron’s 2023 announcement adds a second layer: Gujarat gives incentives equal to 20 percent of the total project cost on top of the Centre’s 50 percent. The cabinet notices state each plant’s investment but not the rupee value of its subsidy, so this article gives none.

Investment figures also move between documents. On 29 February 2024 the cabinet approved Dholera at Rs 91,000 crore, the Assam plant at Rs 27,000 crore and CG Semi at Rs 7,600 crore. A Lok Sabha reply of 1 April 2026, published by PIB, gives Rs 91,526 crore, Rs 27,120 crore and Rs 7,584 crore. The table below uses the later figures.

On 15 July 2026 the cabinet approved a second phase, Semicon 2.0, with an outlay of Rs 1,27,500 crore.

Twelve approvals, five producing

PlantApprovedInvestment (Rs crore)Status in official or company statements
Micron, assembly and test, Sanand, GujaratJune 202322,516Opened and shipping, 28 February 2026
Tata Electronics fab with PSMC of Taiwan, Dholera, Gujarat29 February 202491,526Under construction; first fab due in 2028
Tata assembly and test, Jagiroad, Assam29 February 202427,120Pilot chips reported 3 October 2026
CG Semi (CG Power, Renesas, Stars), Sanand29 February 20247,584Inaugurated for commercial production, 4 July 2026
Kaynes Semicon, Sanand2 September 20243,307Commercial production began March 2026
HCL and Foxconn display driver chips, near Jewar, Uttar Pradesh14 May 20253,706Groundbreaking, February 2026
3D Glass Solutions packaging, Bhubaneswar, Odisha12 August 20251,943Groundbreaking, April 2026
SiCSem silicon carbide fab, Bhubaneswar, Odisha12 August 20252,066Support agreement signed, May 2026
CDIL, Mohali, Punjab12 August 2025117Production line launched, 17 September 2026
ASIP Technologies, Andhra Pradesh12 August 2025480No milestone found in official releases
Crystal Matrix gallium nitride display fab, Dholera, Gujarat5 May 20263,936 for both May unitsApproved
Suchi Semicon, Surat, Gujarat5 May 2026(see above)Production line launched, 17 September 2026

The HCL and Foxconn row follows the Lok Sabha reply, which lists a display driver unit in Uttar Pradesh under Vama Sundari Investments (Delhi) with Foxconn as partner, at the same 20,000 wafers a month that the May 2025 cabinet notice gives for HCL and Foxconn.

The five that are shipping

Micron’s Sanand plant was the first project approved. The company opened it on 28 February 2026 and handed Dell Technologies a first batch of memory modules for laptops “made in India for India”. It converts DRAM and NAND wafers from Micron’s global manufacturing network into finished memory and storage products. Micron said in June 2023 that operations would start in late 2024. It now expects to assemble and test tens of millions of chips there in 2026 and hundreds of millions in 2027, and the Lok Sabha reply puts capacity at about 14 million units a week.

Kaynes Semicon, approved on 2 September 2024, began commercial production in March 2026 according to the mission’s timeline. CG Semi is a CG Power venture with Renesas of Japan and Stars Microelectronics of Thailand. Its first building, called G1, opened as a pilot line on 28 August 2025 with a peak of about 0.5 million units a day, and a second building is due by the end of 2026 to reach about 14.5 million a day, according to PIB. When Prime Minister Narendra Modi inaugurated the plant on 4 July 2026 he said it could deliver 20 crore units a year and voiced confidence in a target of 500 crore.

On 17 September 2026 Modi launched production lines at CDIL in Mohali, which makes power devices such as MOSFETs and diodes, and at Suchi Semicon in Surat. PIB counts them with Micron, Kaynes and CG Semi as the five operating units. Suchi was approved on 5 May 2026.

Which made in India chip came first

The answer depends on who is counting, and five dates compete. Union Minister Ashwini Vaishnaw inaugurated CG’s pilot line on 28 August 2025, and its chips were meant for customer qualification. Five days later he presented the first set of “Made-in-India chips from a pilot line” to the Prime Minister, PIB’s wording. Kaynes shipped 900 intelligent power modules to the US firm Alpha & Omega Semiconductor on 15 October 2025 and called them India’s first commercially manufactured multi-chip modules, a claim that comes from the company’s own filing. Micron followed on 28 February 2026 with its first commercial shipment.

The fifth claim came on 17 September 2026, when PIB listed “India’s first commercial QFN chip” by Suchi Semicon and eInfochips among that day’s announcements. In every case the chip was assembled and packaged in India. Micron’s release says its wafers come from its global manufacturing network. None of the three fabs on the approved list is producing yet. India does have a government laboratory, the Semi-Conductor Laboratory in Mohali, which had fabricated 20 student-designed chips by August 2025.

Dholera, and the process node that moved

The Dholera fab was approved on 29 February 2024 with PSMC (Powerchip Semiconductor Manufacturing Corp) of Taiwan as technology partner, for 50,000 wafer starts a month. The cabinet notice named high performance compute chips on 28 nanometre technology and power management chips as its products. A node, in chip talk, is a generation of manufacturing process named in nanometres, and a smaller number is a newer process.

On 17 July 2026 Bloomberg reported, citing people it did not name, that the fab would run mainly on 90 nanometre technology. A Tata Electronics spokesperson replied that the plan had always been to start with 55 and 90 nanometres and then add 28, and the company describes the fab’s range as 28 to 110 nanometres, according to Outlook Business and TrendForce. TrendForce notes that the Tata Sons annual report for the year to March 2025 had identified 28 nanometres. PSMC spokesperson Eric Tang said technology transfers usually begin with more mature nodes and that 28 is the most advanced node in the licence.

The date moved as well. TrendForce says Tata had earlier targeted commercial production by the end of 2026 and reports that Vaishnaw said it is now expected in mid-2028. We found no published date for 28 nanometre output. PIB’s Semicon 2.0 notice of 15 July says only that the first fab is scheduled to be commissioned in 2028.

What is still unbuilt

Tata’s assembly plant at Jagiroad is the nearest of the unfinished large projects. Assam Chief Minister Himanta Biswa Sarma said on 3 October 2026 that the first cleanroom was ready and pilot chips were being made, Autocar Professional reported, and a formal inauguration by the Prime Minister is expected in December 2026 or January 2027. The plant is designed for up to 48 million units a day.

The HCL and Foxconn unit near Jewar broke ground in February 2026 and is designed for 20,000 wafers and 36 million units a month. The 3D Glass Solutions packaging plant in Bhubaneswar broke ground in April 2026, and the silicon carbide fab in the same Info Valley park, which PIB called the country’s first commercial compound fab, signed its support agreement in May 2026. The gallium nitride display fab at Dholera, approved on 5 May 2026, has no stated start date, and the Rs 3,936 crore figure covers it and Suchi Semicon together.

The most advanced process named for any approved fab is 28 nanometres. The Semicon 2.0 notice says the research pillar will now work on more advanced nodes with centres in India and abroad. The government’s AI compute programme rents tens of thousands of GPUs to startups, as our piece on Indian-language AI describes. Advanced semiconductors are among the components India’s defence industry still imports.

Dr Randhir Thakur, chief executive of Tata Electronics, told the SEMICON India 2026 audience on 17 September that construction of the Dholera fab and the Jagiroad plant is on track, PIB reported. The same release says Applied Materials plans a $5 billion investment in India over the next decade and Lam Research about Rs 10,000 crore for a silicon-component plant.

Share
Copied!

Sources & further reading

  1. PIB: Cabinet approves Semicon 2.0, with an outlay of Rs 1,27,500 crore (15 July 2026)
  2. PIB: Semicon India Programme, Lok Sabha reply with the list of approved projects (1 April 2026)
  3. PIB: Cabinet approves three more semiconductor units (29 February 2024)
  4. PIB: Cabinet approves one more semiconductor unit, Kaynes Semicon (2 September 2024)
  5. PIB: Cabinet approves semiconductor unit in Uttar Pradesh, HCL and Foxconn (14 May 2025)
  6. PIB: Cabinet approves units in Odisha, Punjab and Andhra Pradesh (12 August 2025)
  7. PIB: Cabinet approves two more semiconductor units, Crystal Matrix and Suchi Semicon (5 May 2026)
  8. PIB: CG Power OSAT pilot line inaugurated at Sanand (28 August 2025)
  9. PIB: Prime Minister presented with first set of Made-in-India chips (2 September 2025)
  10. PIB: Prime Minister inaugurates the CG Semi facility in Sanand (4 July 2026)
  11. PIB: Prime Minister inaugurates SEMICON India 2026 (17 September 2026)
  12. India Semiconductor Mission: programme page and timeline
  13. Micron: Celebrates Opening of India's First Semiconductor Assembly and Test Facility (28 February 2026)
  14. Micron: Announces New Semiconductor Assembly and Test Facility in India (22 June 2023)
  15. Kaynes Technology stock exchange filing: first IPM multi-chip modules shipped from Sanand (15 October 2025)
  16. Autocar Professional: Tata Electronics begins semiconductor pilot in Assam (5 October 2026)
  17. Outlook Business: Tata Electronics to start India's first chip fab with 90nm technology (17 July 2026, citing Bloomberg)
  18. TrendForce: Tata's India fab reportedly to launch at 90nm instead of 28nm (20 July 2026)

Researched and written with the help of AI tools and edited for accuracy. Provided for general information and discussion only, not professional advice. See our editorial standards and disclaimer. Spotted an error? Tell us.

#semiconductors#india semiconductor mission#tata electronics#micron#dholera#semicon india#chip manufacturing

Enjoyed this? Get the next one.

One good read at a time, straight to your inbox. No spam, unsubscribe anytime.

More in News
Microsoft Wrote AI Safety Rules With One Non-Negotiable Line: If It Can't Be Shut Down, It Doesn't Ship
One lab wrote a constitution for its own AI. Another gave away a 744 billion parameter model without so much as a blog post. Samsung picked a side in the race to unseat Nvidia, and India made its pitch to the world's chipmakers.
Anthropic Just Revealed How Much of Claude Is Now Built by Claude. The Number Is 26 Percent.
Anthropic put a number on how much of Claude now builds Claude, Microsoft wrote its AI a list of things it can never do, a rival CEO called the industry's safety plan a cartel, and two chip equipment giants backed India's semiconductor ambitions with real money.
Dario Amodei Asked the AI Industry to Slow Down Together. Mark Zuckerberg Said No.
Three of the most powerful people in AI spent the week disagreeing about whether to slow down at all, while two governments bet $300 million on a lab built to never act on its own.
← all articles